How to Get an ADU Permit in California: Step-by-Step Guide

California law requires permit decisions within 60 days. Here's exactly what you need, what it costs, and how long it takes by city.

The ADU permit process in California

Every ADU in California requires a building permit from your local jurisdiction. But state law has significantly streamlined the process — most permits must be approved within 60 days, and many cities now offer pre-approved plan programs that can cut that to 2–4 weeks.

1

Pre-application research

Check your city or county's ADU ordinance. Review setback requirements, height limits, and lot coverage maximums for your zone. Many jurisdictions publish ADU handbooks online.

2

Design and plans

Hire an architect, designer, or use a prefab manufacturer's pre-approved plans. Plans must include site plan, floor plan, elevations, and structural/electrical/plumbing details.

3

Submit permit application

Submit your ADU permit application to the local building department. California law requires the agency to deem the application complete or provide a written list of deficiencies within 30 days.

4

Plan check review

The building department reviews plans for code compliance. State law requires ADU permit decisions within 60 days of a complete application. Many jurisdictions now offer over-the-counter approval for pre-approved plans.

5

Pay fees and pull permit

Pay permit fees (typically $5,000–$20,000 depending on city and ADU size), plus any applicable impact fees for schools, parks, or transportation.

6

Construction

Build with a licensed general contractor. Schedule required inspections at each phase: foundation, framing, rough plumbing, rough electrical, insulation, and final.

7

Final inspection and CO

Pass final inspection and receive a Certificate of Occupancy. The ADU is now legal and can be rented.

ADU permit timelines by city

City / CountyPlan Check TimelinePre-Approved Plans?Typical Permit Fees
Los Angeles8–12 weeksYes (pre-approved)$8,000–$18,000
San Diego6–10 weeksYes$7,000–$14,000
San Jose8–14 weeksLimited$10,000–$20,000
Ventura County4–8 weeksYes$5,000–$12,000
Sacramento4–8 weeksYes$5,000–$10,000
Orange County6–10 weeksVaries by city$7,000–$16,000

California ADU setback requirements

Under state law (AB 68), the maximum setback a local jurisdiction can require for a new detached ADU is:

  • Rear setback: 4 feet from the rear property line
  • Side setback: 4 feet from side property lines
  • Height: Up to 16 feet for most detached ADUs; 24 feet within ½ mile of a major transit stop
  • Lot coverage: Cannot exceed local ordinance limit, but state law prohibits limits that effectively prevent ADU construction

What is a pre-approved ADU plan?

Many California cities now offer pre-approved ADU plan libraries — standard designs that have already completed plan check. Homeowners select a plan from the library, pay a modest customization fee, and submit for a simplified permit. Approval can come in as little as 2 weeks because plan review is already complete.

Pre-approved plan programs exist in Los Angeles, Sacramento, San Jose, Ventura County, and many other jurisdictions. Prefab ADU manufacturers also submit their models for pre-approval in multiple California cities, further streamlining permitting.


Frequently asked questions about ADU permits